Proposition S Project List

  •  

     

     

    Safety and Security

    Entry Vestibules (HSE, BWE, MES, NHS, MGE)

    $     225,000

    Upgrades Camera and Audio Systems (WMS, HRE, CSE)

    $       30,000 

    Handicap Accessible Entryway and Addition of Front Desk Window (ECC)

    $       45,000

    Add Corridor at VMS to connect the two largest instructional buildings

    $     400,000

     

    New Construction/Renovation

    WMS – Gym addition/remodel existing space/band room/classrooms/cafe

    $  5,231,000

    CSE – Gym addition and remodel of existing space; addition of curricular space

    $  2,000,000

    NHS – Renovate lecture hall seating; renovate the baseball and softball fields

    $  1,560,000 

    HSE – Develop the existing courtyard into useable space and bring to code

    $     250,000  

    HSE – Renovate the instructional space on the second floor

    $     400,000  

    ECC – Add shading to the playground

    $       55,000

     

    Maintenance/Efficiency

    CSE – Replace the HVAC system

    $  1,552,500   

    CSE – Replace the existing roof

    $     759,000 

    VMS – HVAC replacement

    $     385,000

    VMS – Window replacement (Welcome Center/7th Grade building)

    $     328,440

    MGE – Window replacement

    $     213,486

    NHS – Replace the Lecture Hall Roof

    $     300,000

    HRE – Addition of parking and rerouting traffic flow

    $     600,000

     

    Total Working Budget

    $14,334,426